Wastewater Treatment Projects

 

International City – Palm Water – MBR

 

Test   Project Name :   International City, Dubai
  Client :   Palm Water Company
  Capacity :   1000 m3/day MBR
  Description :   EPC Contract to supply, install, commission, operate and maintain for 24 months of two membrane bioreactor (MBR) unit with the capacity of 500 m3/day each.
         
         

 

International City – Nakheel – SAF

 

  Project Name :   International city - SAF
  Client :   Nakheel
  Model :   1000-SAF
  Capacity :   1000 m3/day
  Description :   Fully packaged and compact sewage treatment plant. The plant consists of 4 parallel lanes, each of 250 m3/day capacity. Each lane includes a Balancing tank, Bioreaction tank, Disinfection tank, Sludge holding tank, Secondary Settling tank, a machinery room, and effluent storage tank.
           

 

ISAF Headquarter – SAF

 

Test   Project Name :   Alliance Const. & Logistic (ACLC)
  End User
:   ISAF Headquarter (NATO)
         
  Model :   EFLOSAF 450 ECS STP
  Capacity :   450m³/day
           
       

 

Dibba Al hisn – Sharjah Municipality – MBR

 

  Project Name :   Dibba Al Hisn, Sharjah, UAE
  Client
:   Sharjah Municipality
  Capicity :   10,000 m3/day Eflo MBR
  Client Need
:   Sewage Treatment for Dibba Al Hisn
  Effluent :   5mg/l BOD, 5mg/l Suspended Solds, 2mg/l NH4
    Description:
:   EPC Contract to Design, supply, install, commission, operate and maintain EFLO MBR

 

 

ADSSC – Mafraq Labor Camp – MBR

 

  Project Name :   ADSSC – Mafraq Labor Camp
  Client :   Abu Dhabi Sewage Services Company
  Model
:   EFLOMBR-30000
  Capacity :   30,000 m3/day
  Description :   Supply, Installation, Testing and Commissioning of 30,000 m3/day sewage treatment plant for labor camp in Mafraq, Abu Dhabi
         

 

ADSSC – Zakher – MBR

 

  Project Name :   Zakher, Al Ain, UAE
  Client
:   Abu Dhabi Sewerage Services Company
  Capicity :   15,000 m3/day Eflo MBR
  Client Need
:   Sewage Treatment for Zakher, Al Ain.
  Description: :   EPC Contract to design, supply, install, commission, operate and maintain Eflo MBR Unit with the capacity of 15,000 m3/day.
           

 

 

ADSSC – Mafraq Phase1 – SBR

 

  Project Name :   Phase 1 of Mafraq WWTP
  Client :   Abu Dhabi Sewerage Services Company
  Capacity :   50,000 m3/day
  Client Need :   To expand the existing capacity by SBR at Mafraq WWTP
  Scope of Work :   Supply, Installation, Testing and Commissioning of 50,000 m3/day Sequencing Batch Reactor (SBR) wastewater treatment plant.

 

 

 

Atlantis – Palm Jumeirah - SAF

 

  Project Name :   EFLO SAF Sewage Treatment Plant
  Client
:   Atlantis - Palm Jumeirah
  Capicity :   2,000 m3/day
  Scope of Work
:   Treatment of sewage from Atlantis hotel. Specially designed EFLOSAF Air Diffusers allow for maximum air contract and flow direction within the biozone.
         
           

 

 

Occidental Mukhaizna – MBR

 

  Project Name :   Reverse Osmosis Desalination Plant
  Client
:   Occidental Mukhaizna LLC Sultanat of Oman
  Capacity :   6000 m3/day
  Client Need :   • Supply of potable water to thermal plant on site for steam generation. The Treatment Plant was specially designed to treat the H2S in the water.
• Vacuum Sewerage System for labor accommodation 5000 inhabitrats, 7km of sewer line, 127 Vacuum Chambers (3”valve).
• 350 m3/day MBR Wastewater Treatment Plant.
  Scope of Work :   Supply, supervision of installation, testing and commissioning of a water treatment plant.
           

 

ABM Military College - SBR

 

  Project Name :   Sewage Treatment Plant Utilizing UF Technology EFLO SBR
  Client :   ABM Military College – Private Engineering Office (PEO), Qatar
  Type & Capacity
:   EfloSBR with UF, 440 m3/day
  Scope of Work :   Design, Manufacturing, Supply, Supervision of Installation, and Commissioning.
  Project Details :   Sewage treatment plant utilizing Ultra-filtration technology to produce potable type water that was 99.7% free of suspended solids and free of viruses for unrestricted irrigation.  Plant incorporated sophisticated primary screening technology and environmentally friendly disinfection with Ultraviolet system.

 

 

 


 

Water Treatment Projects

 

Pernini – US Army - RO

 

  Project Name :   Pernini – US Army - RO
  Client :   Perini Corporation – US Army Corps of Engineers
  Capacity :   40,000 GPD
 
Scope of Work
:   To treat brackish water to use in plant. Potable water supply for site consumption and deionized water supply for fuel treatment in power plant.
         
         

 

Parsons – Riverpure

 

  Project Name :   Parsons – Riverpure
  Client
:   Parsons (Multiple Units)
  Construction Time :   7 Weeks
  Capacity
:   660 cubic meter/day
  Scope Of Work
:   Design, Build, and Installation, of water purification plant with river water intake system
     Plant Configuration :   River water is collected via a floating intake device in to coagulant dosing unit, flocculent dosing unit, and a lamella clarifier, The water is then passed through a media filtration system, activated carbon filtration system, 5 micron cartridge filtration system, UV disinfection system, and finally 1 micron cartridge filtration system. The product water is further disinfected via a post chlorination dosing unit.

 

 

ADDC – Ras Ghurab – RO

 

  Project Name :   ADDC – Ras Ghurab – RO
  End User
:   Abu Dhabi Distribution Company
  Capacity
:   2x300,000 IGPD
  Scope of Work
:   Design, Supply, installation, Testing and commissioning of sea water Reverse Osmosis Modular Plant with four Reverse Osmosis production lanes
  Client Need
:   Supply of potable water, for the island of Ras Ghurab, Abu Dhabi
           

 

Best Water Ajman – SWRO

 

  Project Name :   Best Water Ajman – SWRO
  Client
:   Best Water, Ajman
  Capacity :   300,000 USGPD
  Client Need
:   To produce high quality water for drinking purpose
  Scope Of Work
:   Design, Build, Supply, Installation, and Commissioning of a Seawater Reverse Osmosis Plant
           

 

     

 

ADWEA – Yasat Island – RO

 

  Project Name :   Yasat Island, Abu Dhabi
  Client
:   ADWEA
  Capacity :   2.125 US MGPD
  Client Need
:   Supply of drinking water for island using sea water reverse osmosis desalination plant.
  Scope Of Work
:   Supply, Installation, Testing and Commissioning of 2.125 US MGPD sea water reverse osmosis plant at Yasat Island, Abu Dhabi.
           

 

 

ADDC – Delma Island – SWRO

 

  Project Name :   Delma Island, Abu Dhabi, UAE
  Client
:   Abu Dhabi Distribution Company
  Capacity :   3.3 US MGD SWRO plant
2nd pass 2 US MGD SWRO plant
  Scope of Work
:   Design, Supply, Installation, Commissioning & Maintenance of 3.3 US MGD Sea water Reverse Osmosis Plant and addition of 2nd pass to existing 2 US MGD SWRO plant
         
           

 

 

 


 

Firefighting Projects

 

Madina Tower

 

  Project Name :   Madina Tower - Jumierah Lakes /Dubai
  Consultant :   KEO
  Scope of Work :   Supply ,testing and commissioning of Fire Fighting Pumps
         
         
         

 

Regal Tower

 

  Project Name :   Regal Tower (Dubai)
  Consultant :   M/S Khateeb and Alami
  Scope of Work :   Supply , Testing & Commissioning for Fire Fighting Systems
         
         
         

 

Mazaya Tower

 

  Project Name :   Mazaya Tower (Dubai)
  Consultant :   NEB
  Scope of Work :   Supply , Testing & Commissioning for Fire Fighting Systems
         
         
         

 

Bel Rashid Tower

 

  Project Name :   Bel Rashid Tower (Sharjah)
  Consultant :   Adnan Saffarini
  Scope of Work :   Supply , Testing & Commissioning for Fire Fighting systems
         
         
         

 

DEWA – 400KV Substation at Technology

 

  Project Name :   400kV Substations at Technology
  Client
:   Dubai Electricity Water Authority (DEWA)
  Scope of Work :   Design, Supply, Installation, Testing and Commissioning of Fire Alarm, Water Spray System, Sprinkler System, Fire Pumps, Fire Water Tanks, Fire Extinguishers & Hydrant System.

         
         
           

 

 

DEWA– 400KV Substation (Barsha & Horse Race)

 

  Project Name :   400kV Substations at Barsha & Horse Race
  Client
:   Dubai Electricity Water Authority (DEWA)
  Scope Of Work :   Design, Supply, Installation, Testing and Commissioning of Fire Alarm, Water Spray System, Sprinkler System, Fire Pumps, Fire Water Tanks, Fire Extinguishers & Hydrant System.
         
         
           

 

 

Dubal – Replacement of Fire Suppression System

 

  Project Name :   Replacement of CO2 Fire Suppression System
  Client
:   DUBAL (Dubai, UAE)
  Scope Of Work :   Design, Supply, Installation, Testing and Commissioning of High Pressure CO2 Fire Suppression System for 13 Nos. of Gas Turbine Units
         
         
           

 

 

DEWA – Jabel Ali (STP)

 

  Project Name :   Jabel Ali STP (Sewage Treatment Plant)
  Client
:   Dubai Municipality
  Scope of Work :   Design, Supply, Installation and Commissioning of Fire Alarm, Voice Evacuation, IG100 Fire Suppression System, Water Spray System, Fire Extinguishers & Hydrant System
         
         
           

 

 

DEWA – 400KV Substation (car complex & Dubai Land)

 

  Project Name :   400kV Substations at Car Complex & Dubai Land
  Client
:   Dubai Electricity Water Authority (DEWA)
  Scope Of Work :   Design, Supply, Installation, Testing and Commissioning of Fire Alarm, Water Spray System, Sprinkler System, Fire Pumps, Fire Water Tanks, Fire Extinguishers & Hydrant System.
         
         
           

 

 

ADWEA / Transco – 132/11 KV Substation

 

  Project Name :   132/11 KV Substations at S18 & E16
  Client
:   ADWEA / TRANSCO
  Scope Of Work :   Design, Supply, Installation, Testing and Commissioning of Fire Alarm, High Pressure CO2 Fire Suppression System, Water Spray System, Sprinkler System, Fire Pumps, Fire Water Tanks,  Fire Extinguishers & Hydrant System.